Industrial

The project entailed a new metal building with insulated panels, and a built-out office building of approximately 10,000 square feet. The project includes conference rooms, breakrooms, storage space, mailroom functions, four service bays for light vehicle servicing, 12,000-gallon above grade fuel storage tank, shade canopies, secured masonry fencing along the

The Willie Itule project consisted of a 70,000-square-foot warehouse renovation including the addition of 13,000 square feet of new office space. Work also included coordination to accommodate 30,000 square feet of owner provided cooler/freezer installation. Willmeng performed significant work that was required to accommodate repairs and grinding of the existing

The largest local ice manufacturer desired to double their production capabilities. Work required occupied phase building expansion to minimize disruption to Ice King’s operations during construction. Willmeng facilitated the addition of two new ice machines and two new bagging lines. Work included complete replacement of the critical Reverse Osmosis equipment,

The project consists of a 65,000-square-foot manufacturing facility for HVAC Equipment. Construction included a heavy electrical scope and installation of three bridge cranes. Coordination consisted of raising the roof approximately 25 feet to accommodate the end user who needed 30 tons of crane area. The project was initially over budget,

Hamilton Sundstrand is a global corporation with various business units that design, manufacture and support technologically advanced aerospace and industrial products for worldwide markets. The company provides electric power generating, distribution, management and control systems. Willmeng Construction was invited by RREEF to join the Design/Build team to meet the project

Representing the Valley’s continued industrial resurgence and evolution, Willmeng Construction broke ground on Wentworth West 80, an industrial spec building at 8001 W. Buckley Rd., on August 8. Totaling 379,828 square feet, the building will consist of a cross-dock warehouse and office space. It’s another example of how older, antiquated

The approved expansion of the Loop 202 required Dolphin Casting, a subsidiary of Karsten Manufacturing, to relocate from the manufacturing facility it has occupied for more than 30 years. Dolphin Casting provides metal castings for multiple industries and automated process including shell. Starting in March 2017, Willmeng Construction began a

The September/October issue of AZRE, published by AZ Big Media, consisted of several articles highlighting Willmeng Construction’s activity across the Valley, thought leadership and its support of NAIOP-Arizona. To catch up on what Willmeng is doing in the Valley and what’s coming down the pike, check out the digital issue

Willmeng Construction has finished work at the 98,643-square-foot Falcon Field Business Center in Mesa, which began construction on Nov. 28, 2017. Located at 3110 N. Greenfield Road, the industrial space was constructed by Willmeng Construction, designed by Butler Design Group, and is currently owned and managed by EastGroup Properties, Phoenix. “This site is desirable

A diverse group of dignitaries, city and government officials as well as top executives attended and shared remarks at the groundbreaking of the 617,000-square-foot campus for Northrop Grumman Innovation Systems that will serve as its Launch Vehicle Division Headquarters, situated within a 47-acre mixed-use development along Chandler’s Price Corridor. The landmark project marks